Renewal of kitchens and bathroom contracts

Meeting: 28/09/2021 - Housing Committee (Item 128)

128 Renewal of the kitchens and bathrooms contract pdf icon PDF 135 KB

Minutes:

The existing contract for replacing kitchens and bathrooms was due to end on the 31st March 2022. There was no option for any further contract extension.

 

A report was submitted which explained the proposed procurement process for securing a new contract from 1st April 2022, together with the regime for signing off designs and installations.  

           

            R E S O L V E D – that:

 

A.        the procurement of a three-year kitchen and bathroom replacement contract (commencing on the 1st April 2022) with an option to extend for a further two years, be approved; and

 

B.      authority be delegated to the Executive Head of Communities, in consultation with the Chair and Vice Chair of the Housing Committee, to award the contract to the successful tenderer.